PROFESSIONAL DESIGN/BUILDERS, INC.
ST THOMAS, VIRGIN ISLANDS OF THE U.S. 008022221
Top Industries (NAICS)
| NAICS Code | Obligations | Awards |
|---|---|---|
| 236220 | $9.29M | 17 |
| 237310 | $4.77M | 7 |
Contract Awards
17 awards found
VI DPW STX(001) CM #6 DECREASE CONTRACT AMOUNT BY $3,998.82 EXTEND CONTRACT TIME BY 223 CALENDAR DAYS.
693C7323C000009 VI DPW STX(001) CM #4 INCREASE CONTRACT AMOUNT BY $172,243.24 EXTEND SCHEDULE A BY 121 CALENDAR DAYS. NOTICE TO PROCEED FOR SCHEDULE B IS AUGUST 15, 2024, WITH A CONTRACT COMPLETION DATE OF FEBRUARY 5, 2025.
THE PURPOSE OF MODIFICATION NO. P00016 IS FOR REA 01 - COST INCURRED TROUBLESHOOTING HUMIDITY ISSUES.
VI DPW STX(001) THE PURPOSE OF THIS MODIFICATION IS TO: 1. EXERCISE SCHEDULE B (OPTION 1) IN THE AMOUNT OF $2,372,539.00 AND ADD 175 CALENDAR DAYS. 2. CONTRACT AMOUNT IS INCREASED FROM $2,224,713.00 BY $2,372,539.00 TO $4,579,252.00. 3. CONTRACT
THE PURPOSE OF THIS MODIFICATION NO. P00015 IS FOR THE INSTALLATION OF A SHUT OFF VALVE FOR THE WATERLINE.
THE PURPOSE OF THIS MODIFICATION NO. P00014 IS TO MAKE CHANGES TO THE SCOPE OF WORK OUTLINED IN RFP 23.
THE PURPOSE OF THIS MODIFICATION NO. P00013 IS TO MAKE CHANGES TO THE SCOPE OF WORK OUTLINED IN RFP 21 AND 22.
THE PURPOSE OF THIS MODIFICATION NO. P00012 IS TO MAKE CHANGES TO THE SCOPE OF WORK OUTLINED IN RFP 13, 16, AND 20 AND EXTEND THE PERIOD OF PERFORMANCE FROM FEBRUARY 29, 2024, TO MARCH 29, 2024.
THE PURPOSE OF THIS MODIFICATION NO. P00011 IS TO MAKE CHANGES TO THE SCOPE OF WORK OUTLINED IN RFP 16, 18, AND 19.
THE PURPOSE OF THIS MODIFICATION NO. P00008 IS TO EXERCISE OPTION - CLIN 0008 - LANDSIDE WORK - PV POWER SYSTEM, MAKE CHANGES TO THE SCOPE OF WORK OUTLINED IN RFP 09, 10, 11, AND 12, AND EXTEND THE POP END DATE FROM DECEMBER 4, 2023, TO JANUARY 30, 2
THE PURPOSE OF THIS MODIFICATION NO. P00007 IS TO EXERCISE OPTION CLIN 00007 LANDSIDE WORK - PAVILION REPAIRS.
THE PURPOSE OF THIS MODIFICATION NO. P00006 IS TO MAKE CHANGES TO THE SCOPE OF WORK OUTLINED IN RFP 03, 06, 07, AND 08.
PROJECT VI DPW STX(001): THE PROJECT CONSISTS OF THE INSTALLATION OF TEMPORARY BRIDGES AND STRUCTURAL REPAIRS. THE WORK INCLUDES EMBANKMENT CONSTRUCTION, AGGREGATE BASE, STRUCTURAL REPAIRS, APPROACH WORK, RIPRAP PLACEMENT, GUARDRAIL INSTALLATION, PA
THE PURPOSE OF THIS MODIFICATION NO. P00005 IS TO MAKE CHANGES TO THE SCOPE OF WORK OUTLINED IN RFP 04 AND 05.
THE PURPOSE OF THIS MODIFICATION NO. P00004 IS TO RESTORE THE LOW-VOLTAGE WIRING SYSTEM TO IMPROVE CURRENT AND FUTURE MAINTENANCE WHICH WAS DISCOVERED TO BE IN DISARRAY DURING THE DEMOLITION OF THE FIRST AND SECOND FLOOR HALLWAY CEILINGS.
THE PURPOSE OF THIS MODIFICATION NO. P00003 IS TO ADD MOLD REMEDIATION SERVICES TO THE ATTIC AND THE CONFERENCE ROOM.
REPAIRS TO CRUZ BAY VISITOR CENTER, DOCKS, AND SURROUNDING GROUNDS
Business Details
- UEI
- GJF5K8MKV386
- CAGE Code
- 1KVZ4
- Address
- 4028 ANNA'S RETREAT ST
ST THOMAS, VI 008022221 - Congressional District
- VI-98
- Phone
- 3406905445
Parent Company
PROFESSIONAL DESIGN/BUILDERS, INC.
Data Source
This profile is based on federal contract award data from USAspending.gov.
View on USAspending.gov